How should the project manager work with these risk handling strategies?

A project manager wants to work on understanding the project risks. The project manager works with the integrated project team to develop the risk handling strategies for the identified risks.

How should the project manager work with these risk handling strategies?
A . Review and revise the strategies periodically.
B. Implement the strategies after completing the risk analysis.
C. Implement the strategies immediately.
D. Ensure the strategies are approved by the stakeholders.

Answer: A

Explanation:

Risk handling strategies should be reviewed and revised periodically to ensure they remain effective and relevant as the project progresses. This allows the project manager to adapt tochanging circumstances and minimize the impact of risks on the project.