In the middle of an iteration a team member suggests a new method of doing things. The method provides no value to the end customer, however it may help the team to work more efficiently. The change may require several days of work to implement

How should the project manager respond to the suggestion?
A . The change should be considered and immediately added to the product backlog.
B . The change should be considered and presented to the project sponsor for approval
C . The change should be considered because rt will help the team work more efficiently
D . The change should not be considered because it adds no value to the end customer

Answer: D