How should the project manager respond?

A project manager is managing a hybrid project. After attending an iteration review, a stakeholder tells the project manager that they are very busy and asks why these reviews are held so frequently Record the issue in the issue log and escalate the conflict to the project sponsor for assistance.

How should the project manager respond?
A . Negotiate a reduced review attendance with the stakeholder and update the stakeholder engagement plan to reflect this reduced
B . Discuss with the stakeholder the benefits of the hybrid project and how frequent reviews lead to greater value and less rework
C . Record the issue in the issue log and escalate the conflict to the project sponsor for assistance
D . Explain to the stakeholder that the stakelrolder engagement plan requires their attendance at all reviews

Answer: B