How should the project manager reflect this change in the project?
During project execution, a project manager is informed that most of the project team members have enrolled in the newly implemented work-from-home company policy.
How should the project manager reflect this change in the project?
A . Update the communication styles for enrolled team members in the communications management plan.
B . Update roles and responsibilities for enrolled team members in the responsibility assignment matrix (RAM)
C . Update the stakeholder engagement plan to include the emergency contact information for enrolled team members.
D . Update the resource calendar for enrolled team members in the resource management plan
Answer: A