An agile project team is building a new product. The stakeholders require ongoing
illustration of project business value.
How should the project manager proceed?
A . Prepare performance value reports for the business on an ongoing basis.
B . Include demonstrations of the built portion of the product at the end of every sprint.
C . Prepare a project report for the stakeholders and distribute it weekly.
D . Confirm the minimum viable product (MVP) and demonstrate it to the business when it is ready.
Answer: B