At the end of planning a new project, the project manager needs to schedule the kick-off meeting but is having difficulty finding a common time slot when all necessary stakeholders can be available onsite .
How should the project manager proceed to schedule the kick-off meeting?
A . Email all stakeholders with the objectives of the project and ask for feedback.
B . Wait for a date when all required attendees can be available onsite.
C . Run separate meetings to accommodate everyone’s schedule.
D . Schedule a virtual meeting so onsite and remote stakeholders can attend at the same time.
Answer: D