How should the project manager proceed?

A project manager has joined a company m an unfamiliar industry and has been given a strategically important project Being new, and not fully understanding the interdependences of the various departmental work items, the project manager is unsure of how to plan the project

How should the project manager proceed?
A . Consult the project sponsor and request their feedback
B . Consult the product owner and request a complete prioritization session
C . Consult a senior project manager within the organization and request their expert judgement
D . Consult a senior developer within the organization and request their input.

Answer: C