How should the project manager plan the delivery of the project?
A company that is heavily focused on delivering projects using predictive approaches on-boards a new project manager who uses hybrid approaches. The scope of the project contains a number of unclear requirements.
How should the project manager plan the delivery of the project?
A . Wait for the requirements to be more clear before any further action is taken on the project
B . Ignore the unclear requirements and focus on the delivery plan of the project
C . Escalate the issue of unclear requirements to the management team and wait for final authorization
D . Break down the requirements and prioritize the requirements into iterative work packages
Answer: D