How should the project manager have handled documentation for the project?

During a documentation audit of an international company it was identified that the last version of the project schedule was from one month ago even though the project manager knew it was recently updated.

How should the project manager have handled documentation for the project?
A . Updated the project management plan regularly and had it securely shared with all
stakeholders
B . Assigned a project team member to ensure all project documentation was updated
C . Reviewed the risk register to identify a response plan for the audit
D . Kept documentation in the project management information system (PMIS), and shared it with appropriate stakeholders

Answer: D