How should the project manager handle this?

During the course of a project the project manager’s immediate director is communicating directly with the client to approve changes without the project manager’s knowledge This is causing confusion in the project team where the scope is changing in the background, but only being mentioned in project meetings

How should the project manager handle this?
A . Communicate directly with the director and inform them of the communications management plan
B . Communicate directly with the client stating that any scope changes must go through the project manager
C . Review the stakeholder engagement plan and put in place any existing actions accordingly
D . Discuss the issues with the project team and let them know that the project manager will handle scope changes

Answer: A