How should the project manager handle the different stakeholders?

A client is structured as a matrix organization for an agile project. The project manager is working on-site with key stakeholders from different parts of the organization

How should the project manager handle the different stakeholders?
A . All stakeholders are important, so the project manager should follow directions provided by management and key stakeholders
B . Because there are different perspectives perform a stakeholder analysis and act based on the outcome.
C . The project manager is working on the client’s premises, so follow the directions of all the key stakeholders
D . This is an agile project, so listen only to the directions of the project manager’s supervisor and the functional managers of the organization

Answer: D