A project manager is preparing to start a new project in which the team members are distributed geographically across different countries. The project manager is using the communications management plan to engage the team members and find a communication method that suits everyone.
How should the project manager continually evaluate the effectiveness of the virtual team’s engagement?
A . Collect feedback from the team to discuss alternatives to enhance the communication.
B. Conduct individual meetings to create a trusting environment with team members.
C. Establish periodic face-to-face meetings and address the communication topic.
D. Hold meetings in accordance with the team members’ preferences and availability.
Answer: A