How should the project manager communicate the design to the implementation team?
A project team is completing a design, while another team in a different country is performing implementation.
How should the project manager communicate the design to the implementation team?
A . Send a detailed email with the completed design document.
B. Conduct a workshop with all of the stakeholders.
C. Conduct a workshop with both of the teams.
D. Upload the design documents into the project repository.
Answer: C