Site icon Exam4Training

How should the project manager approach this?

A project manager is working on a large project with a very difficult client. During the course of the project, the project manager realizes that if the project team had a little more time and funding to make some minor changes, the client could realize the benefits of 25% of the project outcomes early.

How should the project manager approach this?
A . Concentrate on the current project milestones.
B . Update the project management plan for this new work.
C . Develop a business case and submit it to the client.
D . Make all the changes and then show the client the results.

Answer: C

Latest PMP Dumps Valid Version with 721 Q&As

Latest And Valid Q&A | Instant Download | Once Fail, Full Refund

Exit mobile version