How should the project manager approach this problem?

A team is holding the first demonstration of the software built to date on a medium-sized project. The product owner has uncovered a number of issues they would like to be addressed before providing approval.

How should the project manager approach this problem?
A . Plan to address the issues through backlog grooming and incorporate them into the next sprint
B . Refer the product owner to the change management plan, then escalate to the steering committee
C . Refer the product owner to the signed business requirement document and explain that the current plan cannot facilitate these changes
D . Tell the product owner the issues will be addressed in the second version of the software

Answer: A