The project team follows a hybrid framework for its delivery. During the execution of a project, the team learns of a new compliance requirement that has to be delivered before any other requirements

How should the project manager address this situation?
A . Ask the team to include the compliance requirement in the current sprint and deliver it.
B . Add the new compliance requirement to the backlog as the technical team does not have any capacity.
C . Include the compliance lead in the stakeholders list and wait for the next status meeting
D . Collaborate with the compliance team member to review and prioritize the requirement’s delivery

Answer: D