How should the project manager address this situation?

Early in the execution phase, a project manager discovers that recent changes in enterprise environmental factors (EEFs) will severely reduce the implementation cost and shorten the project schedule .

How should the project manager address this situation?
A . Meet with the project team to decide how the remaining budget will be spent.
B . Keep the extra budget as management reserve until project closeout
C . Give the team extra time to finish tasks within the original timeline
D . Follow the project escalation policy and communications management plan

Answer: D