How should the project manager address this situation?
A company is moving its headquarters to another city. The project manager responsible for the assignment has been using a predictive approach during the transition. However, the information systems will be migrated using an agile approach. The project manager needs to decide which kind of control to sign with the vendor responsible for migrating the systems.
How should the project manager address this situation?
A . Negotiate payment after all project migration is completed
B . Sign a single agreement for the whole project
C . Use fixed-price increments as user stories are completed.
D . Confirm payment after each project retrospective
Answer: D