How should the project manager address this situation?
A new resource has joined an iterative project team. The project manager notices that the resource is unable to complete the deliverables on time
How should the project manager address this situation?
A . Address the lack of performance by coaching the new team member
B . Discuss options to improve performance with the resource manager
C . Provide performance feedback as part of the retrospective ceremony.
D . Request a more efficient replacement resource from the project sponsor
Answer: A