How should the project manager address the situation?
A labor union contract negotiation is delaying the completion of a project to build a new manufacturing plant. Because the labor contract was due for renewal this year, the project manager documented the negotiation process as a risk to the project. The project was about to start the first phase of equipment installation at the plant when the negotiation began.
How should the project manager address the situation?
A . Meet with the project team to determine options for risk mitigation.
B . Log the issue and follow the planned actions in the risk response plan.
C . Acquire contract resources and submit a change request for the cost impact.
D . Escalate the issue to the steering committee to ask for mitigation support.
Answer: B
Latest PMP Dumps Valid Version with 721 Q&As
Latest And Valid Q&A | Instant Download | Once Fail, Full Refund