How should the program manager demonstrate the program’s progress?

A program is midway through the program delivery phase when a key stakeholder asks if the program is meeting its defined objectives.

How should the program manager demonstrate the program’s progress?
A . Define the key performance indicators (KPIs) for the program’s outcome.
B . Invite the key stakeholder to review the program charter and the program objectives.
C . Provide additional program performance reports to the key stakeholder.
D . Maintain the benefits register and provide it to the key stakeholder.

Answer: C