An agile project has just started, and the backlog is being prioritized. The customer wants to prioritize business value over identified risks.
How should the customer’s request be managed?
A . Accept risks as they decrease over a period of time.
B . Create a risk value profile to track the relative importance of risks.
C . Log and track risks separately as only business value is important.
D . Assess risks together with business value during prioritization.
Answer: D