How should the Consultant use complex work to meet this requirement?

Universal containers want to schedule delivery using field service lightning. Each delivery requires that an installation and safety inspection be performed by different technicians during the same visit. The safety inspection needs to be executed after the installation is completed

How should the Consultant use complex work to meet this requirement?
A . Define start after finish and same day dependencies
B. Define a same start dependency
C. Define same resource and start dependencies
D. Define start after finish dependencies

Answer: A