How should the consultant recommend delivering a successful implementation?
Universal Containers (UC) wants to implement Service Cloud using Agile methodology.
How should the consultant recommend delivering a successful implementation?
A . set a cutoff date of 1.5 months before user acceptance testing for any change requests.
B . Generate continuous feedback from the project team, and adjust the requirements and deliverables accordingly.
C . Deliver the entire project simultaneously so as to present UC with a completed solution.
D . Schedule a meeting with the UC executives at the start of the project to generate all the requirements.
Answer: B
Explanation:
Generating continuous feedback from the project team, and adjusting the requirements and deliverables accordingly is a key principle of Agile methodology. It allows for iterative and incremental development, which can lead to a successful implementation of Service Cloud.
Verified Reference:
https://trailhead.salesforce.com/en/content/learn/modules/agile-basics/agile-basics-principles:
https://trailhead.salesforce.com/en/content/learn/modules/agile-basics/agile-basics-methodologies