How should the consultant recommend delivering a successful implementation?

Universal Containers (UC) wants to implement Service Cloud using Agile methodology.

How should the consultant recommend delivering a successful implementation?
A . set a cutoff date of 1.5 months before user acceptance testing for any change requests.
B . Generate continuous feedback from the project team, and adjust the requirements and deliverables accordingly.
C . Deliver the entire project simultaneously so as to present UC with a completed solution.
D . Schedule a meeting with the UC executives at the start of the project to generate all the requirements.

Answer: B

Explanation:

Generating continuous feedback from the project team, and adjusting the requirements and deliverables accordingly is a key principle of Agile methodology. It allows for iterative and incremental development, which can lead to a successful implementation of Service Cloud.

Verified Reference:

https://trailhead.salesforce.com/en/content/learn/modules/agile-basics/agile-basics-principles:

https://trailhead.salesforce.com/en/content/learn/modules/agile-basics/agile-basics-methodologies

Latest ADX261 Dumps Valid Version with 277 Q&As

Latest And Valid Q&A | Instant Download | Once Fail, Full Refund

Subscribe
Notify of
guest
0 Comments
Inline Feedbacks
View all comments