How should iterations for an agile project be planned?
A . Throughout the project by using iteration reviews to continuously improve quality.
B. Iteratively by the product owner to ensure global optimization.
C. At the beginning of each iteration by pulling from product backlog.
D. At the retrospective meetings to ensure nothing is missed from one iteration to the next.
Answer: C