How should a project manager solve this issue?
Stakeholders in some industries prefer to deal with programmers and system analysts directly, bypassing project managers. This complicates managing resources on projects.
How should a project manager solve this issue?
A . Propose implementing a new project management information system (PMIS).
B . Request a meeting with senior management to escalate the situation
C . Promote adoption of the communications management plan with the project team.
D . Host a team-building event to develop team cohesion and improve communication
Answer: C