Universal Containers does not want the lunch break to interfere with existing scheduled work.
How should a Consultant configure the Scheduling Policy to ensure a 30-minute lunch break that begins every day after 1pm?
A . Create a recurring Service Appointment
B. Create Resource Absences every day.
C. Use appropriate Resource Operating Hours.
D. Use the Resource Availability Rule.
Answer: A