How often should the Nexus Sprint Backlog be adjusted?

How often should the Nexus Sprint Backlog be adjusted?
A . At least every Nexus Daily Scrum
B. Only during Sprint Planning
C. Once a week

Answer: A

Explanation:

At least every Nexus Daily Scrum, the Nexus Sprint Backlog should be adjusted to reflect the current understanding of the work of the Scrum Teams within the Nexus.

Latest SPS Dumps Valid Version with 120 Q&As

Latest And Valid Q&A | Instant Download | Once Fail, Full Refund

Subscribe
Notify of
guest
0 Comments
Inline Feedbacks
View all comments