How much time will there be after a sprint before the next one starts?
A . Enough to deploy the increment and update the product backlog based on the outcome of the sprint review
B. Enough to clean up lingering definition of done points
C. None, a new sprint starts immediately after the end of the previous one
D. At most a week for a one-month sprint
Answer: C
Explanation:
The scrum guide says: "A new Sprint starts immediately after the conclusion of the previous Sprint."