How much time is allowed between the conclusion of the current Sprint and the start of the next Sprint? (Choose the best answer)
A . Enough time for the Product Owner to prepare the Product Backlog for Sprint Planning.
B . Enough time for the last Increment to finish testing.
C . All of the above are allowed.
D . None. A new Sprint starts immediately following the conclusion of the previous Sprint.
E . Maximum of 1 day for Sprints that are time-boxed to 2 weeks.
Answer: D