How much of the Sprint Backlog must be defined during the Sprint Planning event?
How much of the Sprint Backlog must be defined during the Sprint Planning event?
A . Just enough tasks for the Scrum Master to be confident in the Development Team’s understanding of the Sprint.
B . The entire Sprint Backlog must be identified and estimated by the end of the Sprint Planning meeting.
C . Enough so the Development Team can create its best forecast of what is can do, and to start the first several days of the Sprint.
D . Just enough to understand design and architectural implications.
Answer: B
Latest PSM I Dumps Valid Version with 197 Q&As
Latest And Valid Q&A | Instant Download | Once Fail, Full Refund
C
The correct answer should be C, not B.
Hi team! I’ve notice that question n. 14 and question n. 76 are the same but with a different answer. Would you like to check which one is the right one?!? To me sounds correct C. enough so the… Thanks for your attention!