How much of the overall working time should the Product Owner spend with the Developers?
How much of the overall working time should the Product Owner spend with the Developers?
A . At least 15% of the time.
B. As much as required.
C. Min. 50% of the time.
Answer: B
Explanation:
There is no percentage. It has to be spend as much time as needed.