How many tasks does the product-based planning technique describe?
A . One
B . Two
C . Three
D . Four
Answer: D
Explanation:
The product-based planning technique described in PRINCE2 involves four tasks: writing the Project Product Description, creating the product breakdown structure, writing product descriptions, and creating the product flow diagram. These tasks collectively help in planning the project by focusing on the products that will be delivered.
Reference: PRINCE2 Foundation manual, PRINCE2 official resources