Refer to the exhibit.
A network administrator is planning an MPLS and VPLS Martini solution to connect customer sites 1, 2, and 3.
How many pseudowires must the administrator configure?
A . two; two on PE-1, with one connected to PE-2 and PE-3
B . one; one on PE-1, connected to both PE-2 and PE-3
C . four; two on PE-1, one on PE-2, and one on PE-3
D . six; two each on PE-1, PE-2, and PE-3
Answer: D