How many hours of effort should they quote for that task?

The Developers think that it will take 40 hours of effort to implement an API for online payments for the Product they are working on.

How many hours of effort should they quote for that task?
A . 40 hours
B. 45 hours (40 hours + 5 hours as a buffer for distractions, availability issues, and testing).
C. They must not estimate in hours.
D. 35 hours since teams tend to overestimate.
E. 40 to 45 hours

Answer: A

Explanation:

An estimate is not the same as a commitment. Distractions and availability should not be part of the estimate, they can be forecasted from the capability and past performance. Testing should be considered as part of the development estimate according to the Definition of Done. Although usually Agile Teams, prefers other methods, estimate in hours is not forbidden. The Developers who will be doing the work are responsible for the sizing, they decide the method that is useful for them. Therefore, they have to be transparent and open with what they think and with the actual work that is needed without considering distractions or inflating the estimate.

Latest PAL-I Dumps Valid Version with 305 Q&As

Latest And Valid Q&A | Instant Download | Once Fail, Full Refund

Exit mobile version