How is this described in a project task schedule?
A task cannot begin before another task is completed.
How is this described in a project task schedule?
A . requirement
B . dependency
C . consequence
D . determination
Answer: B
Explanation:
A dependency in a project task schedule describes a situation where a task cannot begin before another task is completed. Dependencies ensure that tasks are performed in the correct order to maintain the workflow and project timeline. Axis Technology Specialist documentation highlights the importance of identifying and managing dependencies to ensure smooth project execution and avoid delays.