How is the ‘tailor to suit the project’ principle applied in an agile context?
A . By flexing what is produced to stay in control and deliver value
B. By emphasizing tolerances on what is being delivered
C. By using the Agilometer to assess the project environment
D. By fitting releases into planned management stages
Answer: A