Exam4Training

How is the actual availability of a resource for project assignments calculated?

How is the actual availability of a resource for project assignments calculated?
A . Available hours = Staffed hours – Free hours
B. Free hours = Available hours – Staffed hours
C. Free hours = Staffed hours – Available hours
D. Available hours = Free hours – Staffed hours

Answer: B

Exit mobile version