How does agile address the risk associated with the project not being fully understood at the beginning?

How does agile address the risk associated with the project not being fully understood at the beginning?
A . By allowing a lot of detail at the start
B. By avoiding too much detail at the start
C. By requiring details at the start
D. By preventing the analysis of details at the start

Answer: D