How do you proceed?

You want to plan minor maintenance for a technical object every three months, and major maintenance for the same object once per year.

How do you proceed? Please choose the correct answer.
A . You create a time-based single-cycle plan and define three-month and twelve-month cycles.
B. You create a multiple-counter plan with one counter for months and another for years.
C. You create a performance-based single-cycle plan and estimate the monthly performance of the technical object.
D. You create a strategy plan with both a three-month cycle and a yearly cycle in the strategy.

Answer: A