Exam4Training

How could a service resource’s timesheet be configured to track the total time spent on each step?

universal containers want to track the time a service resource spends on each step of a more complex repair job. This time could include travel, prep and on site time.

How could a service resource’s timesheet be configured to track the total time spent on each step?
A . Relate the timesheet entries to the work order line time
B. Relate the timesheet entries to the service appointment
C. Relate the time sheet to the service appointment
D. Relate the time sheet to the work order line item

Answer: A

Exit mobile version