Your customer defined one distribution cycle in SAP S/4HANA. You need to define a new distribution cycle .
How can you ensure the new cycle is executed only after the existing one is completed?
A. Assign both cycles to the same cycle run group
B. Select iteration in the cycle header of the new cycle
C. Assign each cycle to a different cycle run group
D. Select iteration in the cycle header of both cycles
Answer: A