How can you create an asset under construction? Note: There are 2 correct answers to this questions.

How can you create an asset under construction? Note: There are 2 correct answers to this questions.
A . Automatically, when setting capex cost from an internal order
B . Automatically, when creating an investment measure
C . Automatically, when setting capex cost from a WBS element
D . Manually (transaction AS01), using a specific asset class

Answer: A,C