How can you achive a feasible production plan in case of capacity constraints?

How can you achive a feasible production plan in case of capacity constraints?
A . Select an alternative mode on a resource.
B. Adjust the available capacity.
C. Reduce the planning window
D. Form optimum sequence to reduce setup times
E. Execute an infinite production planning run

Answer: A,B,D