How can you achieve this in Advanced Planning (PP/DS)?

Your production planners must execute planning only for specific resources.

How can you achieve this in Advanced Planning (PP/DS)?
A . Use a propagation range.
B . Use a resource group
C . Use a planning area.
D . Use a planning group.

Answer: B

Explanation:

You can achieve planning only for specific resources in Advanced Planning (PP/DS) by using a resource group. A resource group is a collection of resources that share the same characteristics and can be used interchangeably for production. You can assign a resource group to a product or a production version, and then use the resource group as a selection criterion in the planning board or the product view. This way, you can restrict the planning to only those resources that belong to the resource group.

Reference: SAP S/4HANA Manufacturing for Planning & Scheduling – Implementation Guide, page 25; [SAP S/4HANA Production Planning and Manufacturing Certification Guide], page 79.

Subscribe
Notify of
guest
0 Comments
Inline Feedbacks
View all comments