How can the R3LOAD export / import duration be minimized? There are 2 correct answers to this question.
How can the R3LOAD export / import duration be minimized? There are 2 correct answers to this question.
A . By adjusting the SAP instance profile parameters
B . By using parallel export / import features
C . By defining an alphabetical package export order
D . By splitting of the package files
Answer: B,D