How can the project manager strategize the use of a hybrid approach to the organization?

A company is about to start a complex research project. Due to the level of uncertainty, the project manager recommends the use of a hybrid approach; however, the organization only has experience with predictive projects.

How can the project manager strategize the use of a hybrid approach to the organization?
A . Present the benefits of a hybrid approach to key stakeholders to get their support.
B. Create a project change request to execute the project using a hybrid approach.
C. Send a letter to the project management office (PMO) requesting to use a hybrid approach.
D. Submit a notification to the project team confirming they will be using a hybrid approach on the project.

Answer: A

Latest PMP Dumps Valid Version with 721 Q&As

Latest And Valid Q&A | Instant Download | Once Fail, Full Refund

Subscribe
Notify of
guest
0 Comments
Inline Feedbacks
View all comments