How can the project manager override the default billing rate for the Video Editor within a project?

A client has negotiated a discounted billing rate for video editing in a specific initiative.

How can the project manager override the default billing rate for the Video Editor within a project?
A . Temporarily change the billing rate for the Video Editor in the Workfront system, and then reset it once the client has been billed.
B . Add a new billing rate to all tasks that involve video editing.
C . Add a new billing rate within the project.

Answer: C

Explanation:

In Workfront, billing rates can be customized for individual projects. To apply a negotiated rate for the Video Editor role within a specific initiative, the project manager can add a new billing rate at the project level. This ensures that the rate is applied only to tasks within the project and does not affect the default system-wide rate for other projects.