How can a project manager of a new technology protect validate that the design meets the customer’s needs?
How can a project manager of a new technology protect validate that the design meets the customer’s needs?
A . Deliver a proof of concept (POC)
B . Perform benchmarking
C . Build a context diagram
D . Construct a prototype
Answer: D