How are earliest dates and latest dates of activities scheduled?

How are earliest dates and latest dates of activities scheduled?
A . Earliest dates are scheduled by backward scheduling, and latest dates by copying the earliest dates
B. Earliest dates are scheduled by forward scheduling, and latest dates by backward scheduling
C. Earliest dates and latest dates are scheduled by forward scheduling
D. Earliest dates are scheduled by backward scheduling, and latest dates by forward scheduling

Answer: B